Timing requirement for exploration drilling operations
Casing is usually the most critical item with respect to timing. Most countries impose very strict purchasing procedures (world bank, local agents etc.) that must be followed to insure potential cost recovery
1 Equipment
Casing is usually the most critical item with respect to timing. Most countries impose very strict purchasing procedures (world bank, local agents etc.) that must be followed to insure potential cost recovery. Process should start 12 months before casing is required (3 months to get through the process of selecting a supplier and issuing a purchase order and up . . .