Sequence of Operations - Typical Onshore Well
This article describes the sequence of operations and the general practices for a typical onshore well.
Operations
General Practices
1. Prepare access road and well lease
Minimise environmental impact due to survey/construction
- Prepare environmental report and map
- Obtain final survey of Lat./Long/Evaluation
- Avoid natural drainage routes, significant topographical disruption. Early contractor site inspection
Arrange timely water supply (well/logistics)
2. Construct . . .