Procedure For Running 30” Conductor
Preparation, planning and procedure for running 30" conductor.
Job Preparation
Note: Well must be drilled to depth. Plan on top 30” conductor pipe being 1.285m down from top of cellar. Do not drill extra depth.
Weld stab in float shoe to first joint.
Ensure both cellar jet and submersible pump are working properly.
While tripping
Rig crane in front of casing on driller’s side
Pump out and clean out cellar.
Run cutting leads to floor and ensure adequate . . .