Offshore Rig Moves
This article describes the various issues to be considered for planning an offshore rig move.
1. Well/Jacket Status Well Plugging Prior to Rig Move
- If the current well path is less than 100 ft from any of the existing wells on the jacket, the wells shall be plugged with deep set plug and BPV. After closing SCSSV, pressure above SCSSV to be bled of to 100 psi and after installation of BPV, pressure above to be bled off to zero psi.
- Wells other than mentioned above shall be plugged with . . .