General Liner Cementation Procedure

General Liner Cementation Procedure

Procedure for single stage cementing operations whith an ES cementer and ECP installed:

  1. Prepare 30 bbls spacer 500 (10.5 ppg) in slug pit as per mixing procedure, while circulating.
  2. Set the hanger as per setting procedure, bleed off pressure to 0 psi, then presure test casing to 2500 psi for 10 mins.
  3. Increase pressure in stages to 2000 psi to inflate the ECP.
  4. Continue increasing pressure to 2750 psi to open the ES cementer.
  5. When ES cementer is opened, circulate hole clean.