Completion Preparation
- Completion Engineer to organise pre-job planning meeting at the rig site, with rig and office personnel to discuss the job objective and hazards.
- Prior to displacing well to a completion fluid, ensure that catch cans and trip tank are clean. Flush choke and kill lines from any loose debris. Wash BOP and pull wear bushing then wash BOP again; this operation should be witnessed by DSV.
- If possible when performing clean out for 7” liner, the drill pipe string can be laid down in single while pulling out of hole to . . .