Casing and Liner Running Preparation Guidelines. Preparation for Running Casing and Liner:
1. ENSURE that all casing/liner and associated equipment is delivered to the well site allowing sufficient time for preparation prior to running.
2 ENSURE that when racking the casing/liner the pin and box ends are oriented correctly for running. Also check casing grade, weight and size.
IF... mixed strings are required and they cannot be racked separately ensure that the last string of casing/liner to be run is offloaded and racked first
3. BACK OFF the protectors sufficiently . . .