Best Practices - Drilling 26" section 26” Section - Preparation
In addition to the items specified in the pre-spud section, the following preparation and checks will be performed:
- Pre-cut conductor from ground level. Keep attached in 4 areas with 2” tabs. Install 30” dresser sleeve.
- Test all mechanical surface equipment (Mud Engineer and solid control personnel to check all Mud equipment and inform Drilling Supervisor of any deficiency).
- Pressure test cement and standpipe lines to 7500psi.
- DSV will carry out Rig acceptance checks (Test Top drive functions as per test . . .