7” Liner - Cementing Preparation and Procedure Checklist
- Hold pre-job planning meeting. All equipment to be checked and personnel familiar with the plan.
- The final cement programme to be issued to the rig and approved by the Drilling Superintendent.
- Ensure that BJ needs to blow out water from the lines after performing pressure test to avoid frozen the lines if job is carried out in cold weather.
- Before cement job begins, ensure that the cement is fluffed and transferred from one tank to another tank to make sure it would transfer in . . .