Checklist: Driling 12.25" section
- Test plug ready
- Install wear bushing
- Float valve installed
- BHA on racks and strapped
- Stabilizers, jars strapped and ready to RIH. Check jar hours
- Bits, nozzles, tools and breaker on location
- Bit hand on location
- OBM weighted up
- Get 9 5/8” csg on location, strap, drift, clean and dress. Have bakerlock on location
- Back load 13 3/8” csg
- Make sure Weatherford are on location and ready 1 day prior . . .