7” Liner Running Operations – Preparation checklist

7” Liner Running Operations - Preparation checklist

  • Pre-job planning meeting with all key personnel.
  • Discuss with LWD coordinator during pre-phase meeting regarding download memory data from LWD on last run to lay down tool instead of leaving tools hanging.
  • Use pipe (XT-54) when running 7” BAKER liner hanger RT, in case it is not able to pull the string then the pipe can be backed off.
  • Check if modified thread compound in compliance with API 5A3 (e.g. Lube Seal API Modified) is available as it is recommended to be . . .

    Restricted Content

    Subscribe to view the Content