7" Liner Operations (Running and Cementing)
1. Hold safety meeting with crews before starting running the liner and report in IADC.
2. Make up plug dropping head on single and lay in v door.
Prepare 10m of chicksan lines.
3. Make up and bakerlock shoe track. Test floating equipment
Make up torques: 7" 35# nvam, min 10850 ft.lbs
Opt 11950 ft.lbs