11. Well Testing - Test String Programme Example
*1 5000 psi well testing programme *1.1 Test objectives 1.To test the transition zone to determine the maximum water saturation at which oil will continue to be produced. 2.To determine the extent of the reservoir and the deliverability of the hydrocarbons. 3.To obtain representative samples of reservoir fluids for compositional, PVT analysis. *1.2 Basic data (determined from final log analysis) Tests 2 and 3 are subject to participant approval. For this reason production test time schedules (Section *3.16) and suspension diagram (Section . . .